CDM 2007 Construction phase plan
The CDM regulations were revised in 2015 and this article is no longer current. It is provided here for historical reference only.
For information about the CDM 2015 construction phase plan, see Construction phase plan.
The Construction (Design and Management) Regulations 2007 (CDM regulations), required that on all notifiable projects, a principal contractor is appointed, and that they develop a construction phase plan setting out how health and safety will be managed during the construction of the project.
Notifiable projects are those which last more that 30 days or involve more than 500 person-days of construction work.
The client must not allow work on site to proceed unless a construction phase plan (CPP) has been prepared, at least for the early stages of the works, and arrangements for the development of the rest of the plan (including the incorporation of information from sub-contractors) has been established.
The construction phase plan should be specific to the project (rather than generic), concise and easy to understand (perhaps with explanatory photographs or drawings).
It might include:
- A description of the works.
- Contact details for those involved in the project.
- Roles and responsibilities.
- A description of existing information and where it can be found.
- The health and safety standards to which the works will be carried out.
- Communication, training and monitoring arrangements.
- Pre-construction issues.
- Arrangements for managing the works, such as security, traffic management, site rules and welfare arrangements.
- Assessment of risks.
- Arrangements for managing significant risks.
- Emergency procedures.
- Information about restrictions which may affect the work (such as restrictions imposed by the client).
- Arrangements for creating the health and safety file.
- Circumstances under which risk assessments or method statements should be prepared.
- Sources of other information.
A detailed list of the possible contents of the construction phase plan was published in appendix 3 of Managing Health and Safety in Construction Construction (Design and Management) Regulations 2007 Approved Code of Practice.
The construction phase plan is different from the health and safety file which is prepared by the CDM co-ordinator and provides information allowing future work to the building to be carried out safely.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Electrical contractors need to understand the practical implications.
The real barrier to getting more value from digital technology.
Your guide to The Construction Reset at UKCW Birmingham.
Accommodating the Victorian and Edwardian working woman. Book review.
Rethinking passive fire protection in design
PFP demands the same level of design rigour as structure or services.
38% of Gen Zs feel safe when a fire door is wedged open.
Stunning images from around the world
Shortlist for CIOB’s Art of Building photography competition.
Guidance for conversion of traditional pre-1919 stone buildings.
Industrial heritage in the Ruhr
A marked difference to the fate of industrial landscapes in the UK.
Communities will be able to build their own clean energy.
Why diversity and inclusion matters for SMEs
CIOB’s D&I Charter shows how practical changes can support long-term growth.
Cut electricity bills to power growth
Coalition sends joint letter to the Chancellor.


















Comments